[COMPLETED] Scheduled Maintenance - Data Center Power Maintenance

Dear Valued Customers,


Stage 1: Preparation by Exabytes

Date : 12th Sept 2018

Time: 8.00 PM - 11.00 PM SGT

ETA: 30 mins each


Stage 2: Maintenance by Upstream provider.

Date: 15th Sept 2018

Time: 8.00 PM SGT


Stage 3: Maintenance by Upstream provider.

Date: 6th Oct 2018

Time: 8.00 PM SGT


Maintenance Detail:

 

Our support team will perform stage 1 maintenance to connect all switches and server's power to 

an automatic transfer switch (ATS) 


It is a preparation for our SG data center upstream provider to perform stage 2 and stage 3 power maintenance on the above data/time without downtime.


Maintenance Affects:

During stage 1 maintenance window, certain VPS and shared hosting servers will be facing a short service disruption.

  

Best Regards,

 

Support Team

......................................

Technical Support Department